 |
System Heating specializes in engineered solutions for the repair, retrofit and upgrade of cooling towers for customers with demanding schedules and a high priority on experience, safety and quality. We have developed field procedures and project management methods for the superior delivery of tower reconstruction projects serving critical applications. System Heating is an independent solutions provider. We understand every tower application is unique and we can source a broad range of solutions to best serve our customers needs.
Typical projects include: |
| Client Name |
Job Name |
Prime or Sub Contractor |
| Wright Runstad |
Nordstrom Medical Tower |
Prime |
Complete refurbishment and modifications of 2 cell cooling tower and related building energy upgrades. Located on a 16th floor rooftop, this BAC cooling tower serves a medical facility with critical 24 hour continuous cooling needs. More >
The cooling tower shared a common sump and could not be shut down for refurbishment or maintenance. Crane or helicopter lifts were not an option for replacement of this system. After investigation, our team developed a plan to create two independently operational cells to provide redundancy and facilitate maintenance on one cell without total shutdown. Our team split the tower cells with internal partition wall fabrication and installed new return piping, internal isolation valves, make up, overflow piping, controls, and sensors—all while the tower remained largely on-line. Tower refurbishment including fill, 20% capacity upgrades, coatings, fan shaft, motors, VFD’s, and new distribution were accomplished during a partial cell shutdown. System Heating negotiated and managed financial participation by Seattle City Light as part of an energy conservation project that involved cooling tower work, valve and control revision to over 300 water source heat pumps, VFD installation on pumps and substantial building control revisions. Also, System field-tested a urethane/glass coating system for a large manufacturer on one tower cell for field observation. |
    |
|
| Client Name |
Job Name |
Prime or Sub Contractor |
| Trammell Crow Company |
1001 4th Avenue Plaza |
Prime |
Structural repairs and fiberglass lining installation on 2 Baltimore Air Coil, 3-cell, cooling towers in rooftop mechanical room of 54 floor office tower. More >
Performed structural repairs and fiberglass lining installation on two Baltimore Air Coil, six cell, 40' x 10' cooling towers in rooftop mechanical room. The cooling tower supporting base had degraded and was failing. Heating used this project to test the application of a new type of tank lining consisting of a proprietary resin and primer formulation. Work was performed on schedule during phased cooling tower shutdown. |
   
 
|
| Client Name |
Job Name |
Prime or Sub Contractor |
| City of Tacoma |
Tacoma Municipal Building |
Prime |
Provided turnkey fluid cooler replacement on the Tacoma Municipal building over one weekend. More >
System Heating has experience with turnkey installations on short schedules. This project included substantial structural modifications and included piping, electrical and control work on critical path weekend shutdown schedule at 220’ feet on unprotected rooftop. |
 
 
|
| Client Name |
Job Name |
Prime or Sub Contractor |
| Equity Office |
Wells Fargo Building |
Prime |
Develop a rebuild package that would provide a lasting and quality solution to extend the useful lifespan of this equipment with minimal maintenance requirements. More >
This work was performed on large 3-cell cooling towers serving a 50-story office building in downtown Seattle. The cooling towers were modified in the past with additional capacity upgrades and piping revisions performed by others. However, there was little record of the modifications available. Therefore, our team made physical investigation to determine the fill media and component details in order to quantify necessary material take offs. The owner’s objective was for System to develop a rebuild package that would provide a lasting and quality solution to extend the useful lifespan of this equipment as long as possible with minimal maintenance requirements. System performed extensive fabrication and installation of custom hand laid tank lining to the complete interior of this tower system. Internal stainless louvers were installed to minimize back draft of moist tower discharge, new distributions were retrofit and internal sand filtration piping was removed and replaced. System also, worked with building engineers to support operational testing to resolve flow anomalies caused by fluctuation of basin water levels during isolation of towers.
|
 
 
|
| Client Name |
Job Name |
Prime or Sub Contractor |
| Wright Runstad |
Washington Mutual Tower Sound Attenuators |
Prime |
Replaced 4 large sound attenuators serving cooling tower discharges for the main tower System's with new stainless steel System's.
More >
System performed an acoustical study, and retrofit of sound attenuators with new stainless steel banks serving 243,000 CFM cooling tower discharge serving on 54-story office building. |
   |
| Client Name |
Job Name |
Prime or Sub Contractor |
| Mckinstry Co. |
Confidential Communications Facility |
Sub Contractor |
Planned and completed tower refurbishment of three EVAPCO cooling towers with severe corrosion and other mechanical problems. The cooling towers at the facility served critical data communication equipment in a building with high security criteria.
More >
This project was critical to perform without error. System's team provided pre task planning and turnkey project delivery successfully— including fill media, complete interior coatings, drift eliminators, distribution retrofits and mechanical repairs.
| |